Due to the intricacy of the challenges that arise during the execution of work, a significant amount of the
work that is done does not conform to the one that was intended. Neither on time, quality, nor the price,
which is something that sometimes happens overbugdet. To be successful in overcoming this obstacle, you
will need to have excellent cost, quality, and time management.Using the Value of Results Method is one
of the many ways that construction work may be handled in an efficient and straightforward manner. This
study's objective is to arrive at an estimate of the time and money required to complete the project in
terms of how much it will effect the cost if it happens. Using the Earned Value Analysis approach is the
research method that will be used to determine how to assess the value of the outcomes on project
performance in terms of time and cost as well as the expected amount of time needed to finish the project.
Based on the application of the results value that was studied during a period of 54 weeks, it was
discovered that the completion of the project would experience an acceleration of work, specifically for
74.4 weeks, when the anticipated duration was 76 weeks. This was discovered after the results value was
examined within a period of 54 weeks. In the meanwhile, when it came to the expenses of the job, it did
not come out as expected, which was Rp. 71.424.373.019. The ultimate sum of all costs associated with
the project was Rp 66.081.465.169. The fact that there is a gap of -Rp.5.342.907.850 between the overall
cost of the work and the cost of the plan indicates that the project will be profitable.


Full Text:

PDF


DOI: https://doi.org/10.32502/jbearing.v8i1.6264

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Published by :

Program Studi Teknik Sipil, Universitas Muhammadiyah Palembang

P-ISSN : 2085-6261

E-ISSN : 2623-1409

Email : bearing@um-palembang.ac.id 

 Creative Commons Licence

Bearing : Jurnal Penelitian dan Kajian Teknik Sipil is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.